You have collected the data for a time-cost CPM scheduling model analysis.The time is in days and the project "direct costs" are given here.
The indirect costs for the project are determined on a daily duration basis.If the project lasts 16 days, the total indirect costs are $400; 15 days, they will be $250; 14 days, they will be $200; and 13 days, they will be $100.At what day do we achieve the lowest?
Total project cost (i.e., direct plus indirect costs) ?
A) 16 days
B) 15 days
C) 14 days
D) 13 days
E) 12 days
Correct Answer:
Verified
Q61: Here are the data for a time-cost
Q62: You have collected the data for a
Q63: In CPM analysis, it is generally expected
Q64: Here are the data for a time-cost
Q65: You have just used the network planning
Q67: You have just performed a CPM analysis
Q68: You know when you have arrived at
Q69: You have just used the network planning
Q70: Popular project management software used in mid-sized
Q71: You have the following time and cost
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents