You know when you have arrived at the optimal solution in using the time-cost CPM scheduling model analysis when what happens?
A) You have found the critical path.
B) You have run out of crash time.
C) You no longer have a linear relationship with costs.
D) You have reached the minimum total cost.
E) You have run out of crash costs.
Correct Answer:
Verified
Q62: You have collected the data for a
Q63: In CPM analysis, it is generally expected
Q64: Here are the data for a time-cost
Q65: You have just used the network planning
Q66: You have collected the data for a
Q67: You have just performed a CPM analysis
Q69: You have just used the network planning
Q70: Popular project management software used in mid-sized
Q71: You have the following time and cost
Q72: You have just used the network planning
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents