A company manufactures tractors and lawnmowers. They have received an order for six deluxe custom riding lawnmowers for a local golf course. They must develop a cost estimate for the order. It is estimated that the first lawnmower will take 90 hours of shop time and a 75 per-cent learning curve is expected. The labor rate is $18.00 per hour, and the pricing policy of the company is to charge 2.5 times the cost of labor for the order.
a. How many hours should the sixth lawnmower take?
b. How many labor-hours should the whole order take?
c. What is the customer's price for the whole order?
d. What is the price per lawnmower?
e. If the original time estimate for the first lawnmower is too low, and it actually takes 80 hours for the third lawnmower, what is the labor hour estimate for the first unit?
f. If it actually really takes 80 hours for the third lawnmower, what is the new total labor cost for the entire order?
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q46: An employee was observed over an
Q47: A fast-food stand has a thriving
Q48: The manager at a sewing factory uses
Q49: A manufacturer made a commitment to supply
Q50: Determine the sample size for the following
Q51: A manufacturer made a commitment to supply
Q53: Locksmith Inc. has an order from a
Q54: A company manufactures computer parts. They have
Q55: Based on data from a work-sampling study,
Q56: A furniture manufacturer has an order for
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents