A furniture manufacturer has an order for 20 custom wine cabinets for a large hotel in Hawaii. It is estimated that the first cabinet will take 100 hours of shop time. An 85 percent learning curve is expected. The labor rate is $12.00 per hour. The pricing policy is to charge two times the labor cost for the order.
a. How many hours will the 20th wine cabinet take?
b. How many hours should the whole order take?
c. What is the price of each cabinet?
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q46: An employee was observed over an
Q47: A fast-food stand has a thriving
Q48: The manager at a sewing factory uses
Q49: A manufacturer made a commitment to supply
Q50: Determine the sample size for the following
Q51: A manufacturer made a commitment to supply
Q52: A company manufactures tractors and lawnmowers. They
Q53: Locksmith Inc. has an order from a
Q54: A company manufactures computer parts. They have
Q55: Based on data from a work-sampling study,
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents