What are the three elements of the triple constraint?
A) cost,time,scope
B) cost,time,scale
C) time,scale,scope
D) cost,scale,scope
Correct Answer:
Verified
Q87: A delay of two weeks in an
Q88: If you have to submit a team
Q89: If a project manager had an extra
Q90: The length to complete a project is
Q91: How many predecessors can an activity have?
A)one
B)none
C)two
D)unlimited
Q93: Which of the following is unlikely to
Q94: Quality improvement initiatives are NOT possible without
Q95: Which of the following is a goal
Q96: Which of the following would be used
Q97: To get a project back on time,a