The length to complete a project is equal to ________.
A) the combined time of all the activities
B) the critical path
C) the critical path less the slack time
D) the combined time of all the activities less the slack time
Correct Answer:
Verified
Q85: Events are also known as _.
A)activities
B)milestones
C)accomplishments
D)mini projects
Q86: A Gantt chart is able to tell
Q87: A delay of two weeks in an
Q88: If you have to submit a team
Q89: If a project manager had an extra
Q91: How many predecessors can an activity have?
A)one
B)none
C)two
D)unlimited
Q92: What are the three elements of the
Q93: Which of the following is unlikely to
Q94: Quality improvement initiatives are NOT possible without
Q95: Which of the following is a goal