A delay of two weeks in an activity that isn't on the critical path would result in how long of a delay to the project?
A) two weeks
B) one week
C) It cannot be determined.
D) none
Correct Answer:
Verified
Q82: Product warranties for smart phones are supporting
Q83: A Gantt chart is used primarily for
Q84: The higher the sigma,the fewer the _.
A)processes
B)defects
C)standards
D)complaints
Q85: Events are also known as _.
A)activities
B)milestones
C)accomplishments
D)mini projects
Q86: A Gantt chart is able to tell
Q88: If you have to submit a team
Q89: If a project manager had an extra
Q90: The length to complete a project is
Q91: How many predecessors can an activity have?
A)one
B)none
C)two
D)unlimited
Q92: What are the three elements of the
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents