If a project manager had an extra person to apply to an activity,which activity should be chosen to shorten the project?
A) the longest activity
B) the hardest activity
C) any activity not on the critical path
D) any activity on the critical path
Correct Answer:
Verified
Q84: The higher the sigma,the fewer the _.
A)processes
B)defects
C)standards
D)complaints
Q85: Events are also known as _.
A)activities
B)milestones
C)accomplishments
D)mini projects
Q86: A Gantt chart is able to tell
Q87: A delay of two weeks in an
Q88: If you have to submit a team
Q90: The length to complete a project is
Q91: How many predecessors can an activity have?
A)one
B)none
C)two
D)unlimited
Q92: What are the three elements of the
Q93: Which of the following is unlikely to
Q94: Quality improvement initiatives are NOT possible without
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents