If a Project Manager Had an Extra Person to Apply

Question 89

Multiple Choice

If a project manager had an extra person to apply to an activity,which activity should be chosen to shorten the project?


A) the longest activity
B) the hardest activity
C) any activity not on the critical path
D) any activity on the critical path

Correct Answer: