If the planned corrective actions do not result in an acceptable schedule, then
A) the project should be terminated.
B) the steps for schedule control need to be repeated.
C) the original project plan was best and should be used.
D) the customer should decide what should be done.
Correct Answer:
Verified
Q62: Analyzing the schedule to determine which areas
Q63: The total completion time is 25 days.Task
Q64: Schedule control involves four steps.Place these steps
Q65: With respect to the project schedule, changes
Q66: As the project progresses, the actual finish
Q68: The estimated duration for each activity is
Q69: The total completion time is 25 days.Task
Q70: Free slack is the amount of time
Q71: The key to effective project control is
Q72: A concentrated effort to accelerate project progress
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents