Question 21
Multiple Choice
The _________is the approved budget,usually in a time distribution format,that is used to estimate,monitor,and control the overall cost performance of the project.
Question 22
Multiple Choice
The process of developing an approximation of monetary resources needed to complete project activities is known as:
Question 23
Multiple Choice
There are many causes of variation in project costs.Which of the following accurately describes the nature of this variation?
Question 24
Multiple Choice
The documentation of a project cost estimate generally requires substantial supporting detail to include all of these EXCEPT:
Question 25
Multiple Choice
Which estimating technique uses a statistical relationship to calculate cost or duration based on historical data and other project parameters?
Question 26
True/False
Value engineering is aimed at increasing the value or productivity of a work element while minimizing the cost.
Question 27
Multiple Choice
Projects often include indirect costs that are necessary to keep the organization running,but are not associated with one specific project.Which of the following items are most typically considered to be indirect costs?
Question 28
Multiple Choice
Which estimating technique decomposes the work into lower,more detailed pieces,preferably the lowest level of WBS work elements,for which estimates are prepared and then aggregates them into a total quantity for the project?